PROJECT UPDATE: APEX AT PERRY CROSSING
NOV 9, 2022 With buildings in Phase One being prepared for handoff, Phase Two for Apex at Perry Crossing is in full swing. While certain...
29 views0 comments
CRESTLINE CONSTRUCTION
Oct 7, 20221 min read
PROJECT UPDATE: APEX AT PERRY CROSSING
OCT 7, 2022 Last week, the process of laying down asphalt for the roadways throughout the Apex property began. An important step for...
27 views0 comments
CRESTLINE CONSTRUCTION
Sep 30, 20221 min read
NEW PROJECT: THE RIVI APARTMENTS
SEP 30, 2022 We cannot wait to start our new project in Foley, Alabama: The Rivi Apartments! Stay tuned for updates as we get ready to...
113 views0 comments
CRESTLINE CONSTRUCTION
Sep 16, 20221 min read
FRAMING AT 4 WEST
SEP 16, 2022 With the podium work in final stages, the framing has begun at 4 West. Building on top of an existing structure can have its...
28 views0 comments
CRESTLINE CONSTRUCTION
Sep 2, 20221 min read
APEX AT PERRY CROSSING UPDATE
SEP 2, 2022 As September begins, Apex at Perry Crossing continues making great strides. New roofing his being completed and framing is in...
11 views0 comments
CRESTLINE CONSTRUCTION
Aug 25, 20221 min read
PROJECT UPDATE: APEX
AUG 25, 2022 Some big moves are happening for Apex at Perry Crossing this week. Gunite, a high-pressure mixture of cement, air, and...
21 views0 comments
CRESTLINE CONSTRUCTION
Jul 29, 20221 min read
PROJECT UPDATE: 4 WEST
JULY 29, 2022 The month of July has seen major steps being taken at the 4 West project in Columbia, South Carolina. The post tension...
26 views0 comments
CRESTLINE CONSTRUCTION
Jul 22, 20221 min read
HOLDING VILLAGE INTERIORS COMING TOGETHER
JULY 22, 2022 With the exteriors coming together, the interiors at Holding Village will now make fast progress. Insulation is being...
27 views0 comments
CRESTLINE CONSTRUCTION
Jul 13, 20221 min read
APEX ROADWAYS AND CLUBHOUSE COME TOGETHER
JULY 13, 2022 With foundations for the major buildings established, work to form the roadways through the property has begun. Adding lime...
27 views0 comments
CRESTLINE CONSTRUCTION
Jul 1, 20221 min read
APEX AT PERRY CROSSING UPDATE
JULY 1, 2022 From an empty field to usable space, Crestline changes the landscape of communities and helps them grow and flourish in the...
9 views0 comments
CRESTLINE CONSTRUCTION
Jun 16, 20221 min read
PROJECT UPDATE: HOLDING VILLAGE
JUNE 16, 2022 With the arrival of summer, the end is in sight for Holding Village. Major steps are being done as exteriors finish and...
10 views0 comments
CRESTLINE CONSTRUCTION
Jun 14, 20221 min read
WELCOME TO THE TEAM
JUN 14, 2022 Crestline Construction is excited to announce the addition of John Robitschek as one of our Project Engineers. John recently...
56 views0 comments
CRESTLINE CONSTRUCTION
Jun 10, 20221 min read
PROGRESS AT APEX
JUN 10, 2022 From the snowy months of winter, to under the bright summer sun, work for Apex at Perry Crossing has been progressing by...
19 views0 comments
CRESTLINE CONSTRUCTION
Jun 6, 20221 min read
4 WEST COLUMNS
JUN 6, 2022 At 4 West, concrete is in the process of being poured and the future elevator shafts are being formed. The concrete columns...
27 views0 comments
CRESTLINE CONSTRUCTION
May 20, 20221 min read
PROJECT UPDATE: HOLDING VILLAGE
MAY 20, 2022 May has seen major progress at Holding Village. With the main siding being completed outside, exterior brick facade is being...
13 views0 comments
CRESTLINE CONSTRUCTION
May 12, 20221 min read
SILA VISITS APEX
MAY 12, 2022 Part of how Crestline Construction achieves predictive, positive results is through open collaboration with partners. The...
14 views0 comments
CRESTLINE CONSTRUCTION
May 5, 20221 min read
KICKING OFF 4 WEST IN COLUMBIA
MAY 5, 2022 The 4 West project is now underway in Columbia, South Carolina. Starting with groundwork and the erection of major structural...
148 views0 comments
CRESTLINE CONSTRUCTION
Apr 27, 20221 min read
PROJECT UPDATE: APEX STRUCTURES ARISE
APR 27, 2022 As framing finishes on the clubhouse, building 1 starts coming out of the ground. Rough grading around phase 1 is finalizing...
14 views0 comments
CRESTLINE CONSTRUCTION
Mar 30, 20221 min read
PROJECT UPDATE: APEX AT PERRY CROSSING
MAR 30, 2022 Work continues at Apex at Perry Crossing in Plainfield as the initial excavations are done for the installation of ground...
8 views0 comments
CRESTLINE CONSTRUCTION
Mar 16, 20221 min read
PROJECT UPDATE: HOLDING VILLAGE MARCHES THROUGH MARCH
MAR 16, 2022 With framing being completed on most structures, the installation of brick and siding has begun on the new buildings. The...
12 views0 comments
CONTACT
Inquiries
For any inquiries, questions or commendations, please call: 317-620-6599 or fill out the following form.
Contact Us
Head Office
3333 Founders RD.
Indianapolis, IN 46268
Tel: 317-620-6599
Fax: 123-456-7890
Employment
To apply for a job with Crestline Constuction, please fill out our form on our careers page by clicking the button below.
Get a quote: 317-620-6599
bottom of page